Construction Representation for the

Owner

 

PROJECT SCHEDULE DEMO

Project Start Date: Thu 5/17/01
Project Finish Date: Wed 10/10/01

Top Level Tasks

ID
Task Name
% Complete Duration Start Finish Resource_Names
1
Permit issued
100% 1 day Thu 5/17/01 Thu 5/17/01  
2
Job set up
100% 1 day Fri 5/18/01 Fri 5/18/01 SCC
3
Interior material saved
100% 2 days Mon 5/21/01 Tue 5/22/01 SCC
4
Disconnected plumbing
100% 3 days Mon 5/21/01 Wed 5/23/01 SUB1
5
Disconnected electrical
100% 3 days Mon 5/21/01 Wed 5/23/01 SUB2
6
Demo site wall/pool deck
100% 4 days Wed 5/23/01 Tue 5/29/01 SCC
7
Relocate pool equipt. Temp
100% 2 days Fri 5/18/01 Mon 5/21/01 SUB3
8
Relocate elect. To pool equipt
100% 2 days Tue 5/22/01 Wed 5/23/01 SUB2
9
Dig out footings
100% 2 days Thu 5/24/01 Fri 5/25/01 SCC
10
Form footings
100% 1 day Wed 5/30/01 Wed 5/30/01 SCC
11
Delay due to field conditions
0% 4 days Thu 5/31/01 Tue 6/5/01  
12
Compact footings
100% 1 day Wed 6/6/01 Wed 6/6/01 SCC
13
Compaction test
100% 1 day Thu 6/7/01 Thu 6/7/01 SUB8
14
Dowel / steel footings
100% 1 day Fri 6/8/01 Fri 6/8/01 SCC
15
Footing inspection
0% 1 day Mon 6/11/01 Mon 6/11/01 SUB7
16
Pour footing
0% 1 day Tue 6/12/01 Tue 6/12/01 SCC
17
Block up stem wall
0% 2 days Wed 6/13/01 Thu 6/14/01 SUB6
18
Sleeve for pool / elect equipt.
0% 1 day Wed 6/13/01 Wed 6/13/01 SCC
19
Form clean outs
0% 0.5 days Fri 6/15/01 Fri 6/15/01 SCC
20
Shore up TB back hall
0% 0.5 days Wed 5/30/01 Wed 5/30/01 SCC
21
Open up back hall
0% 1 day Wed 5/30/01 Thu 5/31/01 SCC
22
Dowel in steel
0% 0.5 days Thu 5/31/01 Thu 5/31/01 SCC
23
Col block up back hall
0% 0.5 days Wed 6/13/01 Wed 6/13/01 SUB6
24
Form clean out / shoot
0% 0.5 days Wed 6/13/01 Wed 6/13/01 SCC
25
Inspection on col./stem wall/foyer
0% 1 day Fri 6/15/01 Fri 6/15/01 SUB11.
26
Remove front post
0% 0.5 days Wed 5/23/01 Wed 5/23/01 SCC
27
Remove entry floor
0% 2 days Wed 5/23/01 Fri 5/25/01 SCC
28
Prep / Form entry floor
0% 0.5 days Fri 5/25/01 Fri 5/25/01 SCC
29
Delay due to field conditions
0% 7 days Tue 5/29/01 Wed 6/6/01  
30
Slab elect at entry
0% 1 day Thu 6/7/01 Thu 6/7/01 SUB8
31
Pour stem wall/ foyer/ col
0% 1 day Fri 6/8/01 Fri 6/8/01 SCC
32
Back fill / compacted
0% 2 days Mon 6/11/01 Tue 6/12/01 SCC
33
Slab elect stair area
0% 1 day Mon 6/11/01 Mon 6/11/01 SUB9
34
Slab pool area equipt.
0% 1 day Mon 6/11/01 Mon 6/11/01 SUB6
35
Pool piping inspection
0% 1 day Tue 6/12/01 Tue 6/12/01 SUB11
36
Rough electrical piping inspection
0% 1 day Tue 6/12/01 Tue 6/12/01 SUB11
37
Demo floor for laundry sink
0% 3 days Wed 5/23/01 Fri 5/25/01 SCC
38
Termite treat stair area
0% 1 day Wed 6/13/01 Wed 6/13/01 SUB9
39
Termite inspection
0% 1 day Thu 6/14/01 Thu 6/14/01 SUB3
40
Slab rough steel
0% 1 day Fri 6/15/01 Fri 6/15/01 SCC
41
Form New Grade Beam
0% 1 day Mon 6/18/01 Mon 6/18/01 SCC
42
Slab inspection
0% 1 day Tue 6/19/01 Tue 6/19/01 SUB6
43
Pour stair area slab
0% 1 day Wed 6/20/01 Wed 6/20/01 SCC
44
Demo hall ceiling / floor
100% 2 days Tue 5/29/01 Wed 5/30/01 SCC
45
Demo back roof overhang
0% 2 days Thu 5/31/01 Fri 6/1/01 SCC
46
Remove rest of back cant.
0% 0.5 days Thu 5/31/01 Thu 5/31/01 SCC
47
Frame shorter ext wall
0% 1 day Thu 6/21/01 Thu 6/21/01 SCC
48
Frame int pad out wall
0% 1 day Thu 6/21/01 Thu 6/21/01 SCC
49
Demo upper hall opening
0% 1 day Thu 5/31/01 Thu 5/31/01 SCC
50
Frame new cant. floor
0% 2 days Fri 6/22/01 Mon 6/25/01 SCC
51
Sheath new floor
0% 0.5 days Tue 6/26/01 Tue 6/26/01 SCC
52
Balloon frame ext walls
0% 2 days Tue 6/26/01 Thu 6/28/01 SCC
53
Frame upper cant wall area
0% 2 days Tue 6/26/01 Thu 6/28/01 SCC
54
Scaffold back side
0% 0.5 days Thu 6/28/01 Thu 6/28/01 SCC
55
Sheath all south ext walls
0% 2 days Fri 6/29/01 Mon 7/2/01 SCC
56
Inspected sheathing
0% 1 day Tue 7/3/01 Tue 7/3/01 SUB11
57
Remove/Fill in lower bath window
50% 1 day Fri 6/1/01 Fri 6/1/01 SCC
58
Remove/Fill in guest window
50% 0.5 days Mon 6/4/01 Mon 6/4/01 SCC
59
Fur out stairway walls
0% 2 days Tue 7/3/01 Thu 7/5/01 SCC
60
Fur out upper hall walls
0% 2 days Fri 7/6/01 Mon 7/9/01 SCC
61
Frame out storage closet
0% 1 day Tue 7/3/01 Tue 7/3/01 SCC
62
Frame stairs / landing
0% 5 days Thu 7/5/01 Wed 7/11/01 SCC
63
Extend upper int bearing wall up
0% 1 day Tue 7/10/01 Tue 7/10/01 SCC
64
Remove foyer roof/beam pocket
0% 2 days Fri 6/1/01 Mon 6/4/01 SCC
65
Set new micro lam / fasteners
0% 2 days Tue 6/5/01 Wed 6/6/01 SCC
66
Frame ceiling
0% 2 days Thu 6/7/01 Fri 6/8/01 SCC
67
Inspected hidden connections
0% 1 day Thu 6/7/01 Thu 6/7/01 SUB11
68
Sub floor guest extension
0% 1 day Mon 6/11/01 Mon 6/11/01 SCC
69
Frame new upper front / side walls
0% 2 days Tue 6/12/01 Wed 6/13/01 SCC
70
Frame lower roof/balconey/sheath
0% 3 days Thu 6/14/01 Mon 6/18/01 SCC
71
Remove existing roof tile
100% 0.5 days Tue 6/19/01 Tue 6/19/01 SCC
72
Demo 2nd floor roof
25% 2 days Tue 6/19/01 Thu 6/21/01 SCC
73
Demo old front guest wall
50% 1 day Thu 6/21/01 Fri 6/22/01 SCC
74
Set new trusses / eng.
0% 2 days Fri 6/22/01 Tue 6/26/01 SCC
75
Truss straps
0% 1 day Tue 6/26/01 Wed 6/27/01 SCC
76
Truss strap inspection
0% 1 day Wed 6/27/01 Thu 6/28/01 SUB11
77
Sheath new roof
0% 2 days Thu 6/28/01 Mon 7/2/01 SCC
78
Inspect sheathing
0% 1 day Mon 7/2/01 Tue 7/3/01 SUB11
79
Dry in new roof
0% 1 day Tue 7/3/01 Thu 7/5/01 SUB11
80
Strap all bearing walls / clip
0% 2 days Tue 6/19/01 Wed 6/20/01 SCC
81
Install all front outlookers / soffit
0% 1 day Mon 7/23/01 Mon 7/23/01 SCC
82
Install all back out lookers / soffit
0% 1 day Mon 7/23/01 Mon 7/23/01 SCC
83
Demo G.B. floor
0% 0.5 days Tue 6/5/01 Tue 6/5/01 SCC
84
Strip all trussed ceilings
0% 2 days Mon 7/2/01 Thu 7/5/01 SCC
85
Run roof/balconey metal
0% 2 days Thu 7/5/01 Mon 7/9/01 SUB11
86
Metal and tag inspection
0% 1 day Mon 7/9/01 Tue 7/10/01 SUB11
87
Demo ext. back garage door
0% 0.5 days Thu 5/31/01 Thu 5/31/01 SCC
88
Open kit window wider
0% 1 day Thu 5/31/01 Fri 6/1/01 SCC
89
Install all windows / bucks
0% 1 day Mon 7/2/01 Tue 7/3/01 SCC
90
Install all window / door pans
0% 4 days Tue 7/3/01 Tue 7/10/01 SUB15
91
Back prime all doors / windows
0% 2 days Thu 7/5/01 Mon 7/9/01 SUB19