ID |
Task Name |
% Complete |
Duration |
Start |
Finish |
Resource_Names |
|
1 |
Permit issued |
100% |
1 day |
Thu 5/17/01 |
Thu 5/17/01 |
|
|
2 |
Job set up |
100% |
1 day |
Fri 5/18/01 |
Fri 5/18/01 |
SCC |
|
3 |
Interior material saved |
100% |
2 days |
Mon 5/21/01 |
Tue 5/22/01 |
SCC |
|
4 |
Disconnected plumbing |
100% |
3 days |
Mon 5/21/01 |
Wed 5/23/01 |
SUB1 |
|
5 |
Disconnected electrical |
100% |
3 days |
Mon 5/21/01 |
Wed 5/23/01 |
SUB2 |
|
6 |
Demo site wall/pool deck |
100% |
4 days |
Wed 5/23/01 |
Tue 5/29/01 |
SCC |
|
7 |
Relocate pool equipt. Temp |
100% |
2 days |
Fri 5/18/01 |
Mon 5/21/01 |
SUB3 |
|
8 |
Relocate elect. To pool equipt |
100% |
2 days |
Tue 5/22/01 |
Wed 5/23/01 |
SUB2 |
|
9 |
Dig out footings |
100% |
2 days |
Thu 5/24/01 |
Fri 5/25/01 |
SCC |
|
10 |
Form footings |
100% |
1 day |
Wed 5/30/01 |
Wed 5/30/01 |
SCC |
|
11 |
Delay due to field conditions |
0% |
4 days |
Thu 5/31/01 |
Tue 6/5/01 |
|
|
12 |
Compact footings |
100% |
1 day |
Wed 6/6/01 |
Wed 6/6/01 |
SCC |
|
13 |
Compaction test |
100% |
1 day |
Thu 6/7/01 |
Thu 6/7/01 |
SUB8 |
|
14 |
Dowel / steel footings |
100% |
1 day |
Fri 6/8/01 |
Fri 6/8/01 |
SCC |
|
15 |
Footing inspection |
0% |
1 day |
Mon 6/11/01 |
Mon 6/11/01 |
SUB7 |
|
16 |
Pour footing |
0% |
1 day |
Tue 6/12/01 |
Tue 6/12/01 |
SCC |
|
17 |
Block up stem wall |
0% |
2 days |
Wed 6/13/01 |
Thu 6/14/01 |
SUB6 |
|
18 |
Sleeve for pool / elect equipt. |
0% |
1 day |
Wed 6/13/01 |
Wed 6/13/01 |
SCC |
|
19 |
Form clean outs |
0% |
0.5 days |
Fri 6/15/01 |
Fri 6/15/01 |
SCC |
|
20 |
Shore up TB back hall |
0% |
0.5 days |
Wed 5/30/01 |
Wed 5/30/01 |
SCC |
|
21 |
Open up back hall |
0% |
1 day |
Wed 5/30/01 |
Thu 5/31/01 |
SCC |
|
22 |
Dowel in steel |
0% |
0.5 days |
Thu 5/31/01 |
Thu 5/31/01 |
SCC |
|
23 |
Col block up back hall |
0% |
0.5 days |
Wed 6/13/01 |
Wed 6/13/01 |
SUB6 |
|
24 |
Form clean out / shoot |
0% |
0.5 days |
Wed 6/13/01 |
Wed 6/13/01 |
SCC |
|
25 |
Inspection on col./stem wall/foyer |
0% |
1 day |
Fri 6/15/01 |
Fri 6/15/01 |
SUB11. |
|
26 |
Remove front post |
0% |
0.5 days |
Wed 5/23/01 |
Wed 5/23/01 |
SCC |
|
27 |
Remove entry floor |
0% |
2 days |
Wed 5/23/01 |
Fri 5/25/01 |
SCC |
|
28 |
Prep / Form entry floor |
0% |
0.5 days |
Fri 5/25/01 |
Fri 5/25/01 |
SCC |
|
29 |
Delay due to field conditions |
0% |
7 days |
Tue 5/29/01 |
Wed 6/6/01 |
|
|
30 |
Slab elect at entry |
0% |
1 day |
Thu 6/7/01 |
Thu 6/7/01 |
SUB8 |
|
31 |
Pour stem wall/ foyer/ col |
0% |
1 day |
Fri 6/8/01 |
Fri 6/8/01 |
SCC |
|
32 |
Back fill / compacted |
0% |
2 days |
Mon 6/11/01 |
Tue 6/12/01 |
SCC |
|
33 |
Slab elect stair area |
0% |
1 day |
Mon 6/11/01 |
Mon 6/11/01 |
SUB9 |
|
34 |
Slab pool area equipt. |
0% |
1 day |
Mon 6/11/01 |
Mon 6/11/01 |
SUB6 |
|
35 |
Pool piping inspection |
0% |
1 day |
Tue 6/12/01 |
Tue 6/12/01 |
SUB11 |
|
36 |
Rough electrical piping inspection |
0% |
1 day |
Tue 6/12/01 |
Tue 6/12/01 |
SUB11 |
|
37 |
Demo floor for laundry sink |
0% |
3 days |
Wed 5/23/01 |
Fri 5/25/01 |
SCC |
|
38 |
Termite treat stair area |
0% |
1 day |
Wed 6/13/01 |
Wed 6/13/01 |
SUB9 |
|
39 |
Termite inspection |
0% |
1 day |
Thu 6/14/01 |
Thu 6/14/01 |
SUB3 |
|
40 |
Slab rough steel |
0% |
1 day |
Fri 6/15/01 |
Fri 6/15/01 |
SCC |
|
41 |
Form New Grade Beam |
0% |
1 day |
Mon 6/18/01 |
Mon 6/18/01 |
SCC |
|
42 |
Slab inspection |
0% |
1 day |
Tue 6/19/01 |
Tue 6/19/01 |
SUB6 |
|
43 |
Pour stair area slab |
0% |
1 day |
Wed 6/20/01 |
Wed 6/20/01 |
SCC |
|
44 |
Demo hall ceiling / floor |
100% |
2 days |
Tue 5/29/01 |
Wed 5/30/01 |
SCC |
|
45 |
Demo back roof overhang |
0% |
2 days |
Thu 5/31/01 |
Fri 6/1/01 |
SCC |
|
46 |
Remove rest of back cant. |
0% |
0.5 days |
Thu 5/31/01 |
Thu 5/31/01 |
SCC |
|
47 |
Frame shorter ext wall |
0% |
1 day |
Thu 6/21/01 |
Thu 6/21/01 |
SCC |
|
48 |
Frame int pad out wall |
0% |
1 day |
Thu 6/21/01 |
Thu 6/21/01 |
SCC |
|
49 |
Demo upper hall opening |
0% |
1 day |
Thu 5/31/01 |
Thu 5/31/01 |
SCC |
|
50 |
Frame new cant. floor |
0% |
2 days |
Fri 6/22/01 |
Mon 6/25/01 |
SCC |
|
51 |
Sheath new floor |
0% |
0.5 days |
Tue 6/26/01 |
Tue 6/26/01 |
SCC |
|
52 |
Balloon frame ext walls |
0% |
2 days |
Tue 6/26/01 |
Thu 6/28/01 |
SCC |
|
53 |
Frame upper cant wall area |
0% |
2 days |
Tue 6/26/01 |
Thu 6/28/01 |
SCC |
|
54 |
Scaffold back side |
0% |
0.5 days |
Thu 6/28/01 |
Thu 6/28/01 |
SCC |
|
55 |
Sheath all south ext walls |
0% |
2 days |
Fri 6/29/01 |
Mon 7/2/01 |
SCC |
|
56 |
Inspected sheathing |
0% |
1 day |
Tue 7/3/01 |
Tue 7/3/01 |
SUB11 |
|
57 |
Remove/Fill in lower bath window |
50% |
1 day |
Fri 6/1/01 |
Fri 6/1/01 |
SCC |
|
58 |
Remove/Fill in guest window |
50% |
0.5 days |
Mon 6/4/01 |
Mon 6/4/01 |
SCC |
|
59 |
Fur out stairway walls |
0% |
2 days |
Tue 7/3/01 |
Thu 7/5/01 |
SCC |
|
60 |
Fur out upper hall walls |
0% |
2 days |
Fri 7/6/01 |
Mon 7/9/01 |
SCC |
|
61 |
Frame out storage closet |
0% |
1 day |
Tue 7/3/01 |
Tue 7/3/01 |
SCC |
|
62 |
Frame stairs / landing |
0% |
5 days |
Thu 7/5/01 |
Wed 7/11/01 |
SCC |
|
63 |
Extend upper int bearing wall up |
0% |
1 day |
Tue 7/10/01 |
Tue 7/10/01 |
SCC |
|
64 |
Remove foyer roof/beam pocket |
0% |
2 days |
Fri 6/1/01 |
Mon 6/4/01 |
SCC |
|
65 |
Set new micro lam / fasteners |
0% |
2 days |
Tue 6/5/01 |
Wed 6/6/01 |
SCC |
|
66 |
Frame ceiling |
0% |
2 days |
Thu 6/7/01 |
Fri 6/8/01 |
SCC |
|
67 |
Inspected hidden connections |
0% |
1 day |
Thu 6/7/01 |
Thu 6/7/01 |
SUB11 |
|
68 |
Sub floor guest extension |
0% |
1 day |
Mon 6/11/01 |
Mon 6/11/01 |
SCC |
|
69 |
Frame new upper front / side walls |
0% |
2 days |
Tue 6/12/01 |
Wed 6/13/01 |
SCC |
|
70 |
Frame lower roof/balconey/sheath |
0% |
3 days |
Thu 6/14/01 |
Mon 6/18/01 |
SCC |
|
71 |
Remove existing roof tile |
100% |
0.5 days |
Tue 6/19/01 |
Tue 6/19/01 |
SCC |
|
72 |
Demo 2nd floor roof |
25% |
2 days |
Tue 6/19/01 |
Thu 6/21/01 |
SCC |
|
73 |
Demo old front guest wall |
50% |
1 day |
Thu 6/21/01 |
Fri 6/22/01 |
SCC |
|
74 |
Set new trusses / eng. |
0% |
2 days |
Fri 6/22/01 |
Tue 6/26/01 |
SCC |
|
75 |
Truss straps |
0% |
1 day |
Tue 6/26/01 |
Wed 6/27/01 |
SCC |
|
76 |
Truss strap inspection |
0% |
1 day |
Wed 6/27/01 |
Thu 6/28/01 |
SUB11 |
|
77 |
Sheath new roof |
0% |
2 days |
Thu 6/28/01 |
Mon 7/2/01 |
SCC |
|
78 |
Inspect sheathing |
0% |
1 day |
Mon 7/2/01 |
Tue 7/3/01 |
SUB11 |
|
79 |
Dry in new roof |
0% |
1 day |
Tue 7/3/01 |
Thu 7/5/01 |
SUB11 |
|
80 |
Strap all bearing walls / clip |
0% |
2 days |
Tue 6/19/01 |
Wed 6/20/01 |
SCC |
|
81 |
Install all front outlookers / soffit |
0% |
1 day |
Mon 7/23/01 |
Mon 7/23/01 |
SCC |
|
82 |
Install all back out lookers / soffit |
0% |
1 day |
Mon 7/23/01 |
Mon 7/23/01 |
SCC |
|
83 |
Demo G.B. floor |
0% |
0.5 days |
Tue 6/5/01 |
Tue 6/5/01 |
SCC |
|
84 |
Strip all trussed ceilings |
0% |
2 days |
Mon 7/2/01 |
Thu 7/5/01 |
SCC |
|
85 |
Run roof/balconey metal |
0% |
2 days |
Thu 7/5/01 |
Mon 7/9/01 |
SUB11 |
|
86 |
Metal and tag inspection |
0% |
1 day |
Mon 7/9/01 |
Tue 7/10/01 |
SUB11 |
|
87 |
Demo ext. back garage door |
0% |
0.5 days |
Thu 5/31/01 |
Thu 5/31/01 |
SCC |
|
88 |
Open kit window wider |
0% |
1 day |
Thu 5/31/01 |
Fri 6/1/01 |
SCC |
|
89 |
Install all windows / bucks |
0% |
1 day |
Mon 7/2/01 |
Tue 7/3/01 |
SCC |
|
90 |
Install all window / door pans |
0% |
4 days |
Tue 7/3/01 |
Tue 7/10/01 |
SUB15 |
|
91 |
Back prime all doors / windows |
0% |
2 days |
Thu 7/5/01 |
Mon 7/9/01 |
SUB19 |